If you’re building in Lee, Collier, Charlotte, or Sarasota, you’ve probably heard strong opinions on concrete block vs wood frame . Some people swear block is the only “real Florida home.” Others like wood for speed, flexibility, and price.

Here’s the truth: the best choice usually isn’t decided by wall material alone. Your lot, flood zone, roof design, openings, connectors, and the crew’s quality control have more to do with how the home performs and what it costs than the word “block” or “frame” on a proposal.

Below is a practical, Southwest Florida focused comparison of cost, timing, and storm behavior, based on how homes are actually permitted and built here in 2026.

What the Florida Building Code (2026) requires, no matter what you build with

Southwest Florida is not in Florida’s High-Velocity Hurricane Zone (HVHZ). HVHZ rules apply to Miami-Dade and Broward (and related local provisions nearby), not Lee, Collier, Charlotte, or Sarasota. Still, our counties sit in wind-borne debris regions and high wind speeds, so the standard Florida Building Code is already strict.

Under the Florida Building Code 9th Edition (2026) , both concrete masonry (CMU) and wood-frame homes must meet the same big-picture goals:

A home has to resist design wind pressures for your exact site, account for exposure (open water and wide open lots can raise loads), and keep the structure tied together from roof to foundation. That last part is the famous continuous load path . Think of it like a seatbelt system for the house. If one connection is weak, the forces don’t “average out,” they concentrate and fail there.

The code also pushes you toward the same storm priorities regardless of wall type:

  • Impact-rated windows and doors (or tested opening protection) in wind-borne debris areas
  • Proper roof decking attachment and underlayment
  • Verified connectors, straps, clips, and anchor schedules
  • Flood rules that can override everything else if you’re in a FEMA flood zone (elevation, breakaway walls, flood-damage-resistant materials)

So when someone asks, “Which is code-approved?” the answer is both. The real question is which system fits your site, budget, and schedule, and which one your builder executes well.

Cost in Southwest Florida: realistic ranges and what actually moves the price

In 2026, new single-family builds in Southwest Florida commonly land around $175 to $400 per square foot depending on design, location, and finish level. As a rule of thumb, wood-frame homes often fall in the $150 to $350 per square foot range, while concrete block homes more often land around $200 to $400 per square foot . Many projects see block run roughly $25 to $50 per square foot higher than wood, but details can swing that gap up or down.

Here’s a simple way to think about it:

Category Wood-frame home (typical) Concrete block home (typical)
Common build cost range (SWFL, 2026) $150 to $350 per sq ft $200 to $400 per sq ft
Where you feel it most Faster dry-in potential, simpler changes More labor in wall phase, heavier structural feel
Biggest “surprise” cost drivers Opening protection, roof system, shear details Reinforcing, grout, lintels, bond beams

What moves your price more than the wall system:

  • Roof system : metal or tile, thicker underlayment packages, and upgraded fasteners add cost fast
  • Openings : impact-rated glass, large sliders, and big front doors can be a major line item
  • Connectors and hold-downs : straps, clips, uplift hardware, and shear wall schedules vary by design
  • Elevation and foundation type : stem wall, fill, piles, or raised slabs in flood zones can dwarf “block vs frame” savings
  • Finishes : cabinets, flooring, countertops, and trim packages often decide whether you’re at $220 or $320 per square foot

This is also where your contract structure matters. A cost-plus home builder model can work well in Southwest Florida because the market changes quickly after storms and during busy seasons. Look for transparent pricing , meaning you can see real invoices, line-item budgets, and what’s being paid, not just allowances that feel fine until they don’t. If you want a clearer picture of how a local team approaches budgeting and execution, start with Southwest Florida custom home construction.

Build time in Lee, Collier, Charlotte, and Sarasota: where schedules really get stuck

Everyone wants a clean answer on timeline. The more honest answer is that schedules behave like traffic on I-75: the distance is fixed, but one crash changes the whole day.

In 2026, a typical construction window (from ground break to finish) is often:

  • Wood-frame : about 6 to 12 months
  • Concrete block : about 9 to 12 months

Total project time is longer once you include design, engineering, selections, and permits. In many cases, design and permitting alone take 3 to 5 months , and Collier can run longer than other counties depending on review load and the complexity of the plans.

Why block can take longer on site: the wall phase is labor heavy and sequential. You stack block, reinforce, grout, pass inspections, then move on.

Why wood can still take a long time: framing can fly, but “fast framing” doesn’t equal “fast move-in.” Mechanical rough-ins, drywall, tile, cabinetry, and trim still take time, and they depend on trade availability.

Common Southwest Florida bottlenecks that hit both systems:

  • Truss and roofing lead times (often weeks, and longer after major storms)
  • Inspection availability (some areas experience backlogs during peak build season)
  • Trade scheduling (good crews are booked out, especially October through April)
  • Weather (summer rain can slow exterior progress and cause material protection issues)

The best timeline saver is a realistic pre-construction plan: long-lead items ordered early, clean permitting docs, and a builder who keeps inspections and trades queued up.

Storm performance: what fails first in hurricanes, and how to make either system stronger

Most hurricane losses don’t start with walls “giving up.” They start when wind finds a weak spot, then water follows.

Research and post-storm field work keep pointing to a few repeat problems:

  • Roof covering loss that leads to water intrusion
  • Roof-to-wall connection failures that escalate into partial roof loss
  • Broken openings (especially garage doors) that let pressure build inside
  • Soffit and gable-end failures that open pathways for wind-driven rain

That’s why the phrase “continuous load path” matters so much. A concrete block wall can be very strong, but if the roof connection, openings, or roof deck attachment is weak, the house can still take major damage. A wood-frame home can perform very well too, as long as the shear walls, straps, anchors, and roof details are built exactly as designed.

Material-specific tendencies to watch:

Concrete block (CMU) homes in SWFL often do well with wind loads when properly reinforced, grouted where required, and tied into the roof system with the right connectors. Problems show up when reinforcement is missed, grout placement is inconsistent, or lintels and bond beams aren’t built as engineered.

Wood-frame homes can be strong, but they rely heavily on correct nailing patterns, hold-downs, and shear wall layouts. The weak link is usually not the lumber itself, it’s the connections and the workmanship .

If you want performance you can feel during a storm, focus on these upgrades (for either system):

  • Better roof geometry : hip roofs often handle wind better than tall gables, depending on the plan
  • Sealed roof deck / secondary water barrier : reduces water damage even if the roof cover is compromised
  • Opening protection you trust : impact-rated windows and doors, and a rated garage door
  • Verified connectors : clips, straps, and anchors installed and inspected, not assumed

After the home is built, a wind mitigation report can also document the storm features and help with insurance in many cases. If you’re new to the process, see understanding wind mitigation for storm protection.

Quick takeaways for choosing between block and frame

  • If your lot is simple and your budget is tight, wood-frame can make sense, if the plan is engineered and built with strong connectors and opening protection.
  • If you want a more “traditional Florida” wall system and don’t mind a higher wall-phase cost, concrete block is a solid fit, especially when reinforcement and roof connections are done right.
  • For storm behavior, details beat material : roof shape, openings, load path, and water control decide the outcome.

Conclusion: pick the system that fits your site, then build the details like they matter

In Southwest Florida, the concrete block vs wood frame decision is less about arguing and more about matching the structure to your lot, your timeline, and your risk tolerance. Both systems can meet the Florida Building Code, and both can fail if the roof, openings, or connectors are treated like an afterthought.

If you want fewer surprises, insist on transparent pricing , get clear about long-lead items early, and prioritize the storm details that keep wind and water out. The best homes here aren’t defined by block or studs, they’re defined by execution .

By Cutting Edge HNR February 8, 2026
A Cape Coral canal lot sounds simple on paper: buy the land, pick a plan, start building. Then reality hits, seawall questions, flood rules, and a waterfront setback that can shrink your “buildable” yard fast. The good news is that most surprises are preventable. If you know w...